ENVIRONMENTAL FACTORS INFLUENCING CONSTRUCTION TIME AND COST OVERRUNS ON HIGH-RISE PROJECT IN NIGERIA
CHAPTER ONE
Introduction
Construction time: The Nigerian construction industry contributes less to the country’s economy than do manufacturing or other service industries. Of®cially, construction accounted for only 5.5% of the annual gross domestic product (GDP) in 1993 (Langdon, 1994). However, the growth of the Indonesian construction industry has greatly in¯ uenced the country’s economic development. As de®ned in developed countries (Hillebrandt, 1985), con- struction is considered unique in that it can stimulate the growth of other industrial sectors. Hence to consider growth of the construction industry in terms of its contribution to GDP in isolation is somewhat misleading: that is, to do so understates the crucial role played by construction. Therefore, improving construction ef®- ciency by means of cost-effectiveness and timeliness would certainly contribute to cost savings for the country as a whole. Effort directed to cost and time- effectiveness were associated with managing time and cost, which in this study was approached via investigating time and cost overruns of high-rise construction in Nigeria.
Like developing countries, such as Nigeria (Okpala and Aniekwu, 1988; Elinwa and Buba, 1993;
Mans®eld et al., 1994), Saudi Arabia (Assaf et al., 1995) and Malaysia (Yong, 1988), Indonesia suffers from construction time and cost overruns. The intentions
of this paper therefore are:
1. to identify variables in¯ uencing construction time and cost overruns;
2. to group these variables into factors;
3. to analyse the relationship of these factors and thereby enhance understanding of construction delays and cost overruns. Although the research concentrates on Nigeria, the ®ndings should be relevant to all developing countries, as they face similar problems in terms of time and cost overruns on construction and infrastructural development projects (Morris and Hough, 1987). Construction Management and Economics (1997) 15, 83±94 Factors in¯ uencing construction time and cost overruns on high-rise projects in Nigeria
Causes of time and cost overruns
According to Antill and Wood head (1989), time over runs
(delays) can be divided into three categories:
1. those over which neither party to the contract has any control;
2. those over which the construction owner (or his/her representative) has control;
3. those over which the contractor (or any subcontractor) has control.
It is generally recognized that delays of type 1 are part of the contractor’s normal and legitimate monetary
risk, and hence should give neither party grounds for monetary recompense, but that the contract com- pletion date should be extended in order to protect contractors from liquidated damages claims for late completion. Alternatively, in the extreme a contract may be repudiated due to `frustration’. It is also recog- nized that for delays of type 2 the contractor should receive fair and reasonable recompense (cost and time), whereas for type 3 delays the contractor must bear full responsibility.
How do I get this complete project on ENVIRONMENTAL FACTORS INFLUENCING CONSTRUCTION TIME AND COST OVERRUNS ON HIGH-RISE PROJECT IN NIGERIA? Simply click on the Download button above and follow the procedure stated. |
I have a fresh topic that is not on your website. How do I go about it? |
How fast can I get this complete project on ENVIRONMENTAL FACTORS INFLUENCING CONSTRUCTION TIME AND COST OVERRUNS ON HIGH-RISE PROJECT IN NIGERIA? Within 15 minutes if you want this exact project topic without adjustment |
Is it a complete research project or just materials? It is a Complete Research Project i.e Chapters 1-5, Abstract, Table of Contents, Full References, Questionnaires / Secondary Data |
What if I want to change the case study for ENVIRONMENTAL FACTORS INFLUENCING CONSTRUCTION TIME AND COST OVERRUNS ON HIGH-RISE PROJECT IN NIGERIA, What do i do? Chat with Our Instant Help Desk Now: +234 813 292 6373 and you will be responded to immediately |
How will I get my complete project? Your Complete Project Material will be sent to your Email Address in Ms Word document format |
Can I get my Complete Project through WhatsApp? Yes! We can send your Complete Research Project to your WhatsApp Number |
What if my Project Supervisor made some changes to a topic i picked from your website? Call Our Instant Help Desk Now: +234 813 292 6373 and you will be responded to immediately |
Do you assist students with Assignment and Project Proposal? Yes! Call Our Instant Help Desk Now: +234 813 292 6373 and you will be responded to immediately |
What if i do not have any project topic idea at all? Smiles! We've Got You Covered. Chat with us on WhatsApp Now to Get Instant Help: +234 813 292 6373 |
How can i trust this site? We are well aware of fraudulent activities that have been happening on the internet. It is regrettable, but hopefully declining. However, we wish to reinstate to our esteemed clients that we are genuine and duly registered with the Corporate Affairs Commission as "PRIMEDGE TECHNOLOGY". This site runs on Secure Sockets Layer (SSL), therefore all transactions on this site are HIGHLY secure and safe! |