Select Currency
Translate this page

DESIGN AND IMPLEMENTATION OF A COMPUTERIZED PRODUCTION SCHEDULER SYSTEM (A CASE SUDY OF OKIN BISCUIT OFFA, KWARA STATE)

Format: MS WORD  |  Chapter: 1-5  |  Pages: 52  |  821 Users found this project useful  |  Price NGN5,000

  DOWNLOAD THE FULL PROJECT

DESIGN AN IMPLEMENTATION OF A COMPUTERIZED PRODUCTION SCHEDULER SYSTEM (A Case Sudy Of Okin Biscuit Offa, Kwara State)

 

CHAPTER ONE

1.0 Introduction

Scheduling is a representation of the time necessary carry out a task and should take account of the technical requirement of the task, marketing forecast and available capacity.

Scheduling is a programme of work to be done or a planned event in a faculty production scheduling.

 A PRODUCTION SCHEDULER: A product scheduler shows the technique through which set of production tasks in a factory can be assigned to machines or personal that will be responsible to a carryout such as tasks, using principle of assignment. There must be an equal number of tasks to the machine or personal available to carry out.

           A product scheduling shows plan for the Manufacturing or a production of a particular products. This plan must be perfectly carried out to minimize the cost of production of the products in the factory. Thus, task time, number of proceeds and the number of available resources are input for considering using assignment technique.                 

ASSIGNMENT TECHNIQUES: This is used to allocate job to machine in computing. The cost of a production job. Therefore, the computerization of production scheduler, using assignment techniques would like to device a minimum cost assignment of a job to a production.

1.1 Historical Background Of The Case Study

Okin biscuit limited, Offa was incorporated in December 1998 by chief E.O Adesoye after his visit to Indian and tries of Mr. Kiswadala, Mr. P.E Keshavan and Mr. Vigay were given the task to monitor the project, as a result of this the structuring and construction of the factory started immediately and at the same time the shipment and installation of the machineries into the factory was between December   1978 and June 1980. Immediately after the completion of the factory structure and the machine installation Mr. Keshwadala was made the general manager company while Mr. P.K Jesharan was appointed the maintenance Engineer of the company, However, the first production of Biscuit started on 2nd of June 1980 with the coaster brand. This brand was still in market when another brand called short cake came out in 1984.

SHORT CAKE: This short cake product affected the sales of the coaster brands at the initial stage due to its sweetness but later in the years, there was equilibrium in their sales and it has made it possible to found in biscuit within outside Nigeria.

However, the company initially started with the following department are: Production Engineering, Accounts and administrative department, but with expansion of its production capacity, the marketing and security Department, was introduced to facilitate the prompt sales and marketing of their products and security of the products by monitoring the works for not stealing biscuit. The company in 1996 introduced another fine products called CABIN, while is still in market but nevertheless, the company has produced some biscuits, which has been out of production such as GEM biscuits.

1.2 Organizational Structure of the Case Study

Okin biscuit limited is structured and organized into various departments namely: production, accounts, engineering, marketing, security and administrative department in which each department is headed by a manager and each section is headed by sectional leader.

However, the General Manager overseas all activities in the company in which some responsibilities are assigned to the various head of department.

ORGANIZATION CHART

PRODUCTION DEPARTMENT

The production manager heads production department. This department into five section viz: mixing, cutting oven, packing and store section.   

These section are headed by three supervisors who are rotated on the three working shift.

•      MIXING SECTION: This section is assigned the responsibility of mixing the various ingredients that are required for the baking of the biscuit.

•      CUTTING SECTION: This section is where the mixed biscuits ingredients are cut into shape before it will get into the baking oven.

•      OVEN SECTION: In this section the cut biscuit is baked with an aid of canvass belt, which will carry out the cut biscuit along the oven down to the parking section

•      PACKING SECTION: This section is responsible for packing, selection and supplying biscuits to the machine that will help in sealing the biscuits into the cattophones and at the same time the total sealing of the carton is done here.  

•      STORE SECTION: This section is assigned with responsibility of keeping both the raw materials for the production and finished products.

The assumption made is that each stage has three different machines which can handle the intended work effectively but the vary capabilities. This research work centre on how these machines can be combined together in order to achieve our  aim of profit maximizing and cost minimization. This project work will dare not extorting its tentative beyond the specified of biscuits production.

1.3 Significance of the Study

This project work is mainly design for a schedule as:

•      The representative which should be as  flexible as possible to enable the representation of schedules of different application with different resources and jobs.    

•      Support of scheduling tasks initiated either by a user or durative improvement.

•      Scheduling tasks an immediately feedback and to fasten the optimization algorithm

•      A schedule while should be an object that can be copied efficiently

ACCOUNTING DEPARTMENT: The accounting is headed by chief accountant who is responsible to the General manager for any financial matter. This department is responsible for taking care of the financial aspect of the company.It is also pivot to all other department  concerning money or any other financial report of the organization. They serve as  put where customer pay biscuit bought in the factory. The cashier manager who is responsible for coordinating the payment of staff salaries supervisors the salary aspect of the company. The department also works in collaboration with store section in payment for raw materials brought into the company.

ENGINEERING DEPARTMENT: The engineering department is the department that is responsible for the daily maintenance of the machineries that are used in the production of the biscuit

Engineering department is divided into two sections namely; electrical and mechanical engineering department. The chief engineers are appointed in which one is responsible for monitoring electrical cases of the machineries and the others.

1.4 Aims and Objectives of the Project

•      The purposes of this  research work is to decides the variable that goes into the decision making process in job scheduling of goods and services.             

•      The project work is also aimed at looking into problems associated with job scheduling and a suitable solution using computer design automation.

•      The project works will also investigate analyze current manual possess of production scheduling at Okin biscuit Nigeria limited and to introduce computer into this process, using assignment, introduce computer into the process, using assignment techniques .       

•      The overall objectives of this project work are to elinate  inappropriate projection scheduling process of the organization under study and there would be a proper minimization of production period and thus maximization of profit.

1.5 Statement of the Project

The problem of this study is to evaluate the manual means of scheduling the job, then develop a means to tackled these difficulties by using computer system.

1.5.1 Research Question

The research work is embarked with questions as:

•      Does this production scheduling described  as a problem of satisfying temporal constraints

•      Would the new proposal system serve as a guide to several objectives functions

•      What will be the relation that mapped on a satisfaction degree, which evaluates how good this constraints, is satisfied in the actual schedule?

•      Does the scheduling system optimally determine when and on  what machine steps are  to be possessed or handled?

1.6 Scope of the Project         

This project work covered three stages out of four stages involve in the production of biscuits, the three stages; mixing, cutting and baking stages.

The assumption made is that each stage has three different machines which can handle the intended work effectively but with vary capabilities. This research work centers on how these machines can be combined together in order to achieve our aim of profit maximizing and cost minimization this project work will dare not escorting its tentative beyond the specified of biscuit production.

 

 

  DOWNLOAD THE FULL PROJECT

DESIGN AND IMPLEMENTATION OF A COMPUTERIZED PRODUCTION SCHEDULER SYSTEM (A CASE SUDY OF OKIN BISCUIT OFFA, KWARA STATE)

Not The Topic You Are Looking For?



For Quick Help Chat with Us Now!

+234 813 292 6373

+233 55 397 8005


HOW TO GET THE COMPLETE PROJECT ON DESIGN AND IMPLEMENTATION OF A COMPUTERIZED PRODUCTION SCHEDULER SYSTEM (A CASE SUDY OF OKIN BISCUIT OFFA, KWARA STATE) INSTANTLY

  • Click on the Download Button above.
  • Select any option to get the complete project immediately.
  • Chat with Our Instant Help Desk on +234 813 292 6373 for further assistance.
  • All projects on our website are well researched by professionals with high level of professionalism.

Here's what our amazing customers are saying

Gbadamosi Solomon Oluwabunmi
Lasu
Swift delivery within 9 minutes of payment. Thank you project master
Excellent
Abdulrahman Jibrin
Nti Abaji
Nice one work prompt delivery tanx
Very Good
Uduak From Uniuyo
IProjectMaster is the best project site for students. Their works are unique and free of plagiarism!
Excellent
Abdul Mateen Iddrisu
UDS
At first I taught is a site full of fraudsters until I saw my project in my Gmail after my payment.. THANK YOU IPROJECTMASTER and May God the almighty bless u guys abundantly
Excellent
Azeez Abiodun
Moshood Abiola polytechnic
I actually googled and saw about iproject master, copied the number and contacted them through WhatsApp to ask for the availability of the material and to my luck they have it. So there was a delay with the project due to the covid19 pandemic. I was really scared before making the payment cause I’ve been scammed twice, they attended so well to me and that made me trust the process and made the payment and provided them with proof, I got my material in less than 10minutes
Very Good
Abdulrazak Bello Marsha
Usman Dan fodio University
It was quite a better guide for project and paper presentation purpoting. Many thanks.
Average
Adam Alhassan Yakubu
UDS
Excellent work and delivery , I promise to share my testimonies everyone in need of this kind of work. You're the best
Excellent
Oluchi From Michael Opara University
If you are a student and you have not used iprojectmaster materials, you are missing big time! iprojectmaster is the BEST
Excellent
JONNAH EHIS
Ajayi Crowther University, Oyo
I was scared at first when I saw your website but I decided to risk my last 3k and surprisingly I got my complete project in my email box instantly. This is so nice!!!
Excellent
Abraham Ogbanje
NATIONAL OPEN UNIVERSITY OF NIGERIA
At first I was afraid.. But I discovered they are legit. I will bring more patronize
Very Good

FREQUENTLY ASKED QUESTIONS

How do I get this complete project on DESIGN AND IMPLEMENTATION OF A COMPUTERIZED PRODUCTION SCHEDULER SYSTEM (A CASE SUDY OF OKIN BISCUIT OFFA, KWARA STATE)?

Simply click on the Download button above and follow the procedure stated.

I have a fresh topic that is not on your website. How do I go about it?

How fast can I get this complete project on DESIGN AND IMPLEMENTATION OF A COMPUTERIZED PRODUCTION SCHEDULER SYSTEM (A CASE SUDY OF OKIN BISCUIT OFFA, KWARA STATE)?

Within 15 minutes if you want this exact project topic without adjustment

Is it a complete research project or just materials?

It is a Complete Research Project i.e Chapters 1-5, Abstract, Table of Contents, Full References, Questionnaires / Secondary Data

What if I want to change the case study for DESIGN AND IMPLEMENTATION OF A COMPUTERIZED PRODUCTION SCHEDULER SYSTEM (A CASE SUDY OF OKIN BISCUIT OFFA, KWARA STATE), What do i do?

Chat with Our Instant Help Desk Now: +234 813 292 6373 and you will be responded to immediately

How will I get my complete project?

Your Complete Project Material will be sent to your Email Address in Ms Word document format

Can I get my Complete Project through WhatsApp?

Yes! We can send your Complete Research Project to your WhatsApp Number

What if my Project Supervisor made some changes to a topic i picked from your website?

Call Our Instant Help Desk Now: +234 813 292 6373 and you will be responded to immediately

Do you assist students with Assignment and Project Proposal?

Yes! Call Our Instant Help Desk Now: +234 813 292 6373 and you will be responded to immediately

What if i do not have any project topic idea at all?

Smiles! We've Got You Covered. Chat with us on WhatsApp Now to Get Instant Help: +234 813 292 6373

How can i trust this site?

We are well aware of fraudulent activities that have been happening on the internet. It is regrettable, but hopefully declining. However, we wish to reinstate to our esteemed clients that we are genuine and duly registered with the Corporate Affairs Commission as "PRIMEDGE TECHNOLOGY". This site runs on Secure Sockets Layer (SSL), therefore all transactions on this site are HIGHLY secure and safe!